2021 Grade C Stormwater Pipe Repair Project

(October 2021)  A construction schedule has not been finalized, but construction is anticipated between December 2021 and April 2022.  The timing of this project will depend on winter rains and storm events, as drainage in the storm system must be maintained during the winter. 

Please check back here for more information and updates!

What should I expect?:
Residents near the work will hear noise during the weekday work days from a vacuum/vactor truck used used to clean the pipes. The contractor will have their trucks parked on the sides of the street while working.

The contractor will open lids and grates in order to physically access to the pipes to complete the repair work.  Work areas will be cordoned off with cones and other safety equipment to warn street users away from work areas.


Description of Project:

As part of the Aging and Failing Infrastructure Capital Program, the City is rehabilitating existing stormwater pipes 18 inches and larger throughout the City.  This work will help correct pipe sections that are wearing out faster than their intended operational life and extend the time before more costly and disruptive replacement is required.

Pipes not in need of immediate replacement, but were showing signs of faster wear than normal, were given a grade "C" during a 2018-2019 study of City pipe camera from 2012-2017.  A program of annual rehabilitation activities is planned from 2020 to approximately 2027, in addition to areas of failed pipe replacement during 2019.

This year's pipe rehabilitation work will include 2,485 lineal feet of cured-in-place pipe (CIPP) and 15 small areas of sectional cured-in-place lining (SCIPL).  These methods involve slipping a liner tube into the existing pipe, pressing it against the pipe interior, and curing it to stick the liner uniformly to the interior storm pipe surface.  Repairs will include pipe under the the following neighborhoods and streets:

  • Heatherwood Road Vicinity
  • Heatherstone
  • Huckleberry
  • Village Green Drive
  • Dumas Lane
  • Trillium Boulevard

City Council awarded the 2021 Grade C Stormwater Pipe Repair project to Allied Trenchless at the July 13, 2021 City Council meeting.  The contract awarded is valued at $ 413,875.00.