Seattle Hill Road Paving Update

Seattle Hill Road Paving Update
Posted on 07/16/2020

MILL CREEK, Wash. – The City of Mill Creek will begin paving Seattle Hill Road on Friday, July 17 through Thursday, July 23 as part of the preservation project. These dates are subject to change based on weather conditions. 

The paving will take place between Village Green Drive and 35th Ave SE.

The Seattle Hill Road Preservation Project includes repairing damaged asphalt, overlaying new asphalt, replacing damaged median curbs, upgrading ADA curb ramps and installing accessible pedestrian signals at two intersections between Village Green Drive and 35th Ave SE.

Motorists should expect traffic delays. Traffic control will be in place to facilitate the movement of vehicles through the work zone and maintain access to the residential subdivisions adjacent to Seattle Hill Road. Motorists are encouraged to use alternate routes if possible during this time period.

For additional information, visit: https://www.cityofmillcreek.com/cms/one.aspx?portalId=9100937&pageId=16793058